#BMC on Wednesday has said that 58% of its highly ambitious Mumbai Coastal Road Project (South) has been completed so far. Out of the total 111 hectares, 107 hectares i.e. 97% reclamation has been completed. Similarly, 70% work of the sea wall has been completed.
Out of the 175 monopiles to be constructed under the bridges, 70 have already been constructed which is 40%. Under the project, tunnels of 2.070 km. each are being constructed on both sides. (2/3)
The tunnel from Priyadarshini Park to Netaji Subhash Marg (Marin Drive) has already been completed, while 39% work of the tunnel on the other side has also been completed. The entire Mumbai Coastal Road Project is targeted to be completed by November, 2023. (Ends)
Replugging a report @nauzerbTOI & I did in May this year on the mega project set to change Mumbai’s Western water front @mybmcCoastalRd timesofindia.indiatimes.com