PM Modi Ji on spree of inaugurating different projects! CONgress says that PM Modi Ji takes credit for many Projects Originally started by CONgress.
THIS TIME CONgress IS RIGHT!
I'll give info on atleast 10 such projects where PM Modi Ji is FALSELY taking credit.
1/22
PM Modi Ji on spree of inaugurating different projects! CONgress says that PM Modi Ji takes credit for many Projects Originally started by CONgress.
THIS TIME CONgress IS RIGHT!
I'll give info on atleast 10 such projects where PM Modi Ji is FALSELY taking credit.
1/22
Foundation stone of this project was laid by Indira Khan-Gandhi in 1978. It's just that CONgress Govts in Centre from 1979 to 2014 forgot that any such project was planned.
PM Modi ONLY started ACTUAL work on it since June 2014 & got it completed.
Inauguration: 11 Dec 21
3/22
PM Modi ONLY started ACTUAL work on it since June 2014 & got it completed.
Inauguration: 11 Dec 21
3/22
Original Estimated Cost: ₹93 Cr
Actual Cost: ₹9802 Cr
Escalation of cost happened because PM Modi revived project. Had he also forgotten about project,Cost wouldn't have been incurred at all. So,PM Modi is responsible for Escalated Cost & Project belongs to CONgress.
4/22
Actual Cost: ₹9802 Cr
Escalation of cost happened because PM Modi revived project. Had he also forgotten about project,Cost wouldn't have been incurred at all. So,PM Modi is responsible for Escalated Cost & Project belongs to CONgress.
4/22
Conceptualized by Late PM Atal Bihari Vajpayee Ji in 2003
Approval by UPA Govt: Jan 2009
Work Started: Nov 2011
Sleeping Period of UPA: till May 2014
Work Re-started by PM Modi Ji: June 2014
Inauguration: 26May17
Initial estimated cost(2009): ₹1000Cr
Actua cost:₹2056 Cr
6/22
Approval by UPA Govt: Jan 2009
Work Started: Nov 2011
Sleeping Period of UPA: till May 2014
Work Re-started by PM Modi Ji: June 2014
Inauguration: 26May17
Initial estimated cost(2009): ₹1000Cr
Actua cost:₹2056 Cr
6/22
Proposed in 1999-2000 by Late PM Atal Bihari Vajpayee Ji.
Sanctioned in: 2001-02
UPA Sleeping Period: 2004-2014
Work Re-started: Oct 2014
Inauguration: 29 Oct 2017
Initial estimated Cost: ₹386 Cr
Actual Cost: ₹1150 Cr
All Modi's fault!
8/22
Sanctioned in: 2001-02
UPA Sleeping Period: 2004-2014
Work Re-started: Oct 2014
Inauguration: 29 Oct 2017
Initial estimated Cost: ₹386 Cr
Actual Cost: ₹1150 Cr
All Modi's fault!
8/22
Approved in: Oct 2008
Foundation Stone: Feb 2009
Then UPA pushed project under carpet due to Local Political Issues.
PM Modi Ji got local issues sorted out through consensus. Work Re-started.
Inauguration: Sept 2018
Initial estimated Cost:₹264Cr
Actual Cost:₹605Cr
11/22
Foundation Stone: Feb 2009
Then UPA pushed project under carpet due to Local Political Issues.
PM Modi Ji got local issues sorted out through consensus. Work Re-started.
Inauguration: Sept 2018
Initial estimated Cost:₹264Cr
Actual Cost:₹605Cr
11/22
Eastern Peripheral: 135 Km
Approved in:March 2006
UPA Slept.
Complete & Inaugurated:
27 May 2018
Western Peripheral: 136 Km
Approved in: 2003
Work Started: 2006
UPA Slept.
Complete & Inaugurated:
19 Nov 2018
Combined Initial estimated Cost:₹2699Cr
Actual Cost:₹11000Cr
13/22
Approved in:March 2006
UPA Slept.
Complete & Inaugurated:
27 May 2018
Western Peripheral: 136 Km
Approved in: 2003
Work Started: 2006
UPA Slept.
Complete & Inaugurated:
19 Nov 2018
Combined Initial estimated Cost:₹2699Cr
Actual Cost:₹11000Cr
13/22
Sanctioned by Then PM Deve Gowda in 1997.
Work Started: 2002 under Late PM Atal Bihari Vajpayee Ji.
STALLED by UPA: 2004
Re-started: July 2014
Inauguration: 25 Dec 2018
Initial estimated Cost: ₹1767 Cr
Actual Cost: ₹5960 Cr
15/22
Work Started: 2002 under Late PM Atal Bihari Vajpayee Ji.
STALLED by UPA: 2004
Re-started: July 2014
Inauguration: 25 Dec 2018
Initial estimated Cost: ₹1767 Cr
Actual Cost: ₹5960 Cr
15/22
Why CONgress so concerned about profits of GMR Group? Because Robert Vadra has CLOSE ASSOCIATION with it.
जमाई is important, Not the Nation or Economy!!
Project Revived: June 2015
1st Phase to complete: Jan 2024
Initial estimated Cost:₹5000Cr
Escalated Cost:₹30000Cr
18/22
जमाई is important, Not the Nation or Economy!!
Project Revived: June 2015
1st Phase to complete: Jan 2024
Initial estimated Cost:₹5000Cr
Escalated Cost:₹30000Cr
18/22
Finally....
Foundation Stone: May 2022
To become fully operational: March 2023
Initial estimated Cost:???? (CONgress didn't dare to disclose)
Estimated Cost Now: ₹17930 Cr
20/22
Foundation Stone: May 2022
To become fully operational: March 2023
Initial estimated Cost:???? (CONgress didn't dare to disclose)
Estimated Cost Now: ₹17930 Cr
20/22
Now, Did you get enough proofs that CONgress is correct in saying PM Modi takes credit for projects started ON PAPER by CONgress.
PM Modi must stop acting Great! He JUST completed projects announced ON PAPER by CONgress.
CONgress also would've completed AFTER 50 MORE YRS!
21/22
PM Modi must stop acting Great! He JUST completed projects announced ON PAPER by CONgress.
CONgress also would've completed AFTER 50 MORE YRS!
21/22
खबरदार..Don't you dare to blame CONgress for wasting Taxpayers Money with Delay in Projects. Who told Modi to WASTE money by COMPLETING these Projects? If Modi wouldn't have restarted projects,money wouldn't have been spent. Means No Escalation! ZERO LOSS!
Mudi shud regin!
22/22
Mudi shud regin!